SpaceX disclosed on Nov. 12 that it will pour more than $74 billion into two new artificial‑intelligence supercomputing facilities, one at its Starbase site in Texas and another on a 747‑acre parcel in Cochise County, Arizona. The Texas project is slated for a $24 billion outlay, while the Arizona campus is budgeted at roughly $50 billion. Both sites are designed to generate their own power, with the Arizona complex projected to demand up to 6 gigawatts when fully operational. The announcements come as SpaceX’s AI‑related services comprised 52% of its third‑quarter revenue, according to the company’s SEC filing.

Anthropic Deal Remains Intact Amid Speculation

Elon Musk used his X account to reject media reports that Anthropic might walk away from its long‑term computing agreement with SpaceX. He said the company would "be happy to take the compute back" but expects the opposite. Bloomberg and other sources confirm Anthropic is SpaceX’s largest customer, contributing about 34.5% of Q3 revenue. The contract, valued at up to $120.5 billion, runs through 2029 with monthly payments projected at $3.1 billion once full capacity is deployed. Either party may terminate the deal with 90‑day notice after non‑cancelable periods end in early 2027.

Regulatory Hurdles and Local Opposition

The Arizona development faces a series of regulatory reviews. Cochise County’s Local Emergency Planning Committee approved six safety recommendations in a Nov. 12 meeting, addressing fire protection, battery storage, and emergency response. The county’s next decision is scheduled for Dec. 9, when officials will consider the full application amid public opposition and concerns over the site’s 6‑gigawatt power draw. The Texas facility, by contrast, plans to operate off‑grid, reducing reliance on the public electricity network.

FAQ

What is the size of the AI facilities SpaceX plans to build?

SpaceX intends to build a $24 billion facility at Starbase, Texas, and a roughly $50 billion campus on a 747‑acre site in Cochise County, Arizona.

When can either party terminate the Anthropic‑SpaceX agreement?

Either party may give 90 days' written notice to terminate after the initial non‑cancelable periods end in January 2027 for SpaceX and March 2027 for Anthropic.

What regulatory step is pending for the Arizona project?